Net Zero Connector (NZC) Pipeline
Project Location
Completed near Fort Saskatchewan, AB
Strike Divisions
Pipeline Services
Project Overview
The overall project consists of the construction and installation of ~229kms of 12” steel pipeline for the purpose of transporting CO2 as part of the emerging carbon capture and sequestration technology. The pipeline plays a major role in the development of the carbon capture infrastructure being developed in Alberta’s Industrial Heartland. This project was completed by Canadian Plains Energy Services, a Strike Group company, and their portion of the scope of work included:
Spread 1
- 15.1 Km of NPS 12 steel pipeline
- 6.4 Km of NPS 8 steel pipeline
- 1 NPS 12 and NPS 8 valve site
- 1 NPS 12 Pump Station Tie In
- Multiple Designed HDD crossings