Brine Pond Liner Replacement

Project Locations:

  • Hardisty, Alberta

Strike Divisions:

  • Industrial Services

Project Overview:

Remove and replace the existing liner and leak detection system in a 20-acre Brine Pond.

Scope:

  • Remove and replace the existing liner and leak detection system in the Brine Pond. 77,000 M2 material for each layer x 3 layers.
  • Remove and replace the leak detection system, along with 1100m of perimeter fencing.
  • Haul all material off-site to landfills for disposal.
  • Maintained a day and night shift working 20 hours per day with no days off for approx. 100 days in a row to meet client deadlines while managing snow, high winds and rains throughout execution.