13-17 Multi Well Pad
![](https://www.strikegroup.ca/wp-content/uploads/2024/03/Cenovus-13-17-Multi-Well-Pad-1800px-v2-300x128.jpg)
Project Location:
Edson, Alberta
Strike Divisions:
- Field Services
Project Overview:
Four Well Pad Construction
Scope:
- Fabricated 1800 weld inches, tested, and installed all piping and piping components.
- Install, cut & cap 45 pilings
- Install structural steel and supports
- Build gravel pads and secondary containments
- Complete 150m of 6” pipeline from lease edge to new riser