Gas Debottleneck Phase 2

Project Locations:

  • One Hour NE of Fort McMurray, AB

Strike Divisions:

  • Electrical & Instrumentation

Project Overview:

This project included the Installation of electrical tray, cables and heat trace for two new compressor buildings and equipment for the expansion of debottleneck pipelines at a plant.

Scope:

  • Install vendor compressor buildings and ship loose equipment.
  • Install new cables and supports from electrical building to motors and heat trace.
  • Install interconnecting cables from electrical building to existing plant.

The project was delayed in midsummer due to the wildfire activity in the area. Extended work shifts were required to complete the project as soon as possible for the client.